Mat 01: Life cycle impacts (UK NC 2011 and 2014)

Mat 01: Life cycle impacts (UK NC 2011 and 2014)

Life Cycle Assessment for BREEAM UK NC 2011 and 2014
This guidance supports our IMPACT-compliant and IMPACT-equivalent tools (IMPACT-equivalent has since been renamed to 'LCA for BREEAM UK'), which are designed to achieve Mat 01 exemplary credits by Route 2: Using compliant Life Cycle Assessment software tools. If you are using BREEAM UK NC 2018 see guidance here

If you are working with a BREEAM UK Retrofit and fit-out (RFO) project please note that the tool you have chosen and the guidance here only apply for using One Click LCA for BREEAM UK New construction. For UK Retrofit and fit-out please choose the “LCA for BREEAM int’l and RFO” tool and check our other guidance here
The idea of the Mat 01 credit is to perform a life cycle assessment, analyze the results and report how it helped you to steer the design process to a more sustainable direction.

BREEAM UK Reporting templates

The reporting templates can be used for client reporting as well as to report how the analysis has helped to steer the design process the certification. However, they are not mandatory and other forms of reporting can be used as well. Please find the download files named as follows in the attachments at the bottom of the page:

One_Click_LCA_IMPACT_Equivalent_Result_reporting_template_for_BREEAM_UK_NC_Mat_01_LCA_29_1_2018
One_Click_LCA_IMPACT_Compliant_Result_reporting_template_for_BREEAM_UK_NC_Mat_01_LCA_29_1_2018

Completing an LCA for BREEAM UK NC compliance purposes is a straight forward process 

The required steps are:

  1. Have your Building project ready and select the right tool for the calculations

  2. Create a new design and give it a name of your choice. One Click LCA has two tools that support this credit “IMPACT Equivalent” (LCA for BREEAM UK) and “IMPACT Compliant”. Your license may only contain one of them or both. In that case, you can choose which you wish to use (see explanation at the end of the page).

  3. Check the mandatory scope for required elements from BREEAM UK New Construction 2011 or 2014 from guidance note 8 (GN8). Ensure that materials that are required to be reported as separate building elements are identified as such.

  4. Fill in your project information in One Click LCA by entering the design either manually or by import your data (see different import options here; guidance for data import can be found here).

    If you need help finding the right datasets for your building materials, check our guidance pages for material selection and finding EPDs.

    Use net quantities (amounts of material installed in the building) which shall be accurate to +/- 5 %. For each material, you can adjust the service life based on your product and use the Comment field for additional info (e.g. specify the construction element where the material belongs to). The name is used for report grouping and should support the user to track back to the bill of materials.

    If you are using the LCA for BREEAM UK IMPACT-compliant (IMPACT-compliant tool), make sure to select RICS category for each resource and verify (if necessary, adjust) the wastage share (on site wastage). Material quantities for site wastage should be within +/- 5% of the actual quantities. For resource selection, you can set a filter and display resources from a specific location only (by selecting Show filters and selecting Country). To choose the material data for your project you’ll have two equally good options: to use data only from BRE database or to also choose materials from other databases. You are allowed to use technically similar materials from other markets but in that case, you must apply the local compensation feature. The data localisation settings will be given in the Compensate to local conditions question form. If you only use datasets from BRE database, you must choose project localisation for the local compensation. If you have only used data from BRE database you can leave the first question empty and only choose BRE database in Methodologically consistent and regionally representative LCA data.

    Remember to report the site excavation fuel use. That can be done in the Construction site operations question form.

    Find the compliancy documentation for the tool here.
    Leave the Energy and Water consumption question forms empty.

    If you are using the LCA for BREEAM UK IMPACT-compliant (IMPACT-compliant tool), you have access exclusively to IMPACT average building material database, enabled only for this indicator. The reporting uses automatic grouping based on resource type linked to each material. Find the compliance documentation for the tool here.

    Additionally, you are required to fill in the Energy consumption question form, add ‘0’ to demonstrate that this is not reported. The Water consumption question form can be left empty.

    Add 60 years to the Calculation period question form.

  5. Fill in the Building area question form by entering the GIFA (Gross Internal Floor Area).

  6. Click on the Results page to see the results. To get the BREEAM evidence report, click on more actions. You will then be able to download your results as an Excel spreadsheet.

  7. Explain how LCA has benefited the building by following the instruction here.

  8. Submit the exported Excel file to the BRE together with your BREEAM project number and name.

Two tools for BEEAM UK NC: IMPACT Compliant and IMPACT Equivalent (LCA for BREEAM UK tool)
One Click LCA has two separate calculation tool options for achieving the Mat 01 LCA credits for BREEAM UK: 'LCA for BREEAM UK' and 'LCA for BREEAM UK IMPACT-compliant'.

The main difference between these two calculation tools is the building material database: IMPACT Equivalent (LCA for BREEAM UK tool) will use material manufacturer-specific environmental product declarations while IMPACT Compliant uses IMPACT database which is an average database for UK construction materials. Additionally IMPACT Equivalent focuses on the mandatory credit scope of the materials embodied carbon impacts providing easily understandable results while IMPACT Compliant tool will include a comprehensive life cycle assessment with multiple environmental impact categories and very detailed results. The IMPACT database has a separate license and to use the IMPACT Compliant tool it will have to be separately included to your license.

The available data points in the IMPACT Compliant tool are around 260, while you will have 15.000 + options in the 'LCA for BREEAM UK' tool. For this reason, generally its more accurate to use the 'LCA for BREEAM UK' tool, as the BRE IMPACT database only has a limited amount of generic data.

BREEAM UK Material requirements


1

Substructure

1

Substructure

1

Standard foundations

Mandatory





2

Specialist foundation systems

Mandatory





3

Lowest floor construction

Mandatory





4

Basement excavation (fuel use only)

Mandatory, can be aggregated





5

Basement retaining walls (2.5.2)

Mandatory

2

Superstructure

1

Frame (other than floors)

1

Steel frames

Mandatory





2

Space decks

Mandatory





3

Concrete casings to steel frames

Mandatory, can be aggregated





4

Concrete frames

Mandatory





5

Timber frames

Mandatory





6

Other frame systems

Mandatory



2

Upper floors

1

Floors

Mandatory





2

Balconies

Optional





3

Drainage to balconies

Optional



3

Roofs

1

Roof structure

Mandatory, can be aggregated





2

Roof covering

Mandatory, can be aggregated





3

Specialist roof systems

Mandatory, can be aggregated





4

Roof drainage

Optional





5

Rooflights, skylights and openings

Mandatory





6

Roof features

Optional



4

Stairs and ramps

1

Stair / Ramp structures

Mandatory, can be aggregated





2

Stair / Ramp finishes

Optional





3

Stair / Ramp balustrades and handrails

Optional





4

Ladders / Chutes / Slides

Optional



5

External walls

1

External enclosing walls above ground floor level

Mandatory





2

External enclosing walls below ground level

Mandatory





3

Solar / Rain screening

Mandatory, can be aggregated





4

External soffits

Mandatory





5

Subsidiary walls, balustrades, handrails, railings and
proprietary balconies

Optional





6

Façade access / cleaning systems

Optional



6

Windows and external doors

1

External Windows

Mandatory





2

External doors

Mandatory





3

Walls and partitions

Mandatory



7

Internal Walls and Partitions

1

Walls and partitions

Mandatory





2

Balustrades and handrails

Optional





3

Moveable room dividers

Optional





4

Cubicles

Optional



8

Internal doors

1

Internal Doors

Mandatory, can be aggregated

3

Internal finishes

1

Wall Finishes

1

Finishes to walls

Mandatory, can be aggregated



2

Floor Finishes

1

Finishes to floors

Mandatory, can be aggregated





2

Raised access floors

Mandatory, can be aggregated



3

Ceiling Finishes

1

Finishes to ceilings

Mandatory, can be aggregated





2

False ceilings

Mandatory, can be aggregated





3

Demountable suspended ceilings

Mandatory, can be aggregated

4

Fittings, Furnishing and Equipment





Optional

5

Services (note: category may be used for operational/in-use fuel and energy use)





Optional

 8

 External works

 2

Roads, Paths and Pavings

 1

 Roads, paths and pavings

Mandatory





 2

 Special surfacings and pavings

Mandatory



 3

Soft Landscaping, Planting and Irrigation Systems






 4

Fencing, Railings and Walls


Fencing and railings

Mandatory






Walls and screens

Mandatory






Retaining walls

Mandatory






Barriers and guardrails

Optional



5

External fixtures



Optional



6

External drainage



Optional



7

External services



Optional

A5

Construction Installations (may be based on a rate per m2 NIA)





Mandatory

Attachments


    • Related Articles

    • Mat 01: Life cycle impacts (UK NC 2018)

      Life Cycle Assessment for BREEAM UK NC 2018 This guidance supports ‘LCA for BREEAM UK’  and ‘LCA for BREEAM UK IMPACT-compliant’ tools, which are designed to achieve BREEAM Mat 01 seven credits and three exemplary credits. For BREEAM UK NC 2011 and ...
    • Mat 01: Life Cycle Impacts (BREEAM Int & RFO)

      Mat 01 LCA for BREEAM Intl & RFO This guide is for LCA in compliance with BREEAM International 2013/2015/2016 as well as BREEAM-NOR 2016, BREEAM España and BREEAM UK RFO 2014 for Mat 01 Life cycle impacts. The LCA allows achieving full 100 % of the ...
    • Mat 02: Environmental impacts from construction products (UK NC 2018)

      Here's how to get your Mat02 credit for the BREEAM UK 2018 scheme The Mat02 credit can be achieved by using the 'LCA for BREEAM UK' tool Select the Mat02 EPD classification on the 'Building materials' question form:  Get your Mat02 output on the ...
    • Man 02: Life cycle cost and service life planning (UK NC 2014)

      This guidance helps you to successfully complete your calculations for BREEAM Life Cycle Costing credits in One Click LCA with our automated LCC tool. Please note that this guidance only applies to BREEAM UK NC 2014, but the LCC  tool can also be ...